How It Works

Send us your plans and soil report and the Future Found system is then designed by our structural engineers.  We then send you foundation plans with calculations.  Once this is complete the system is delivered all ready to go.

Read our Psi-Therm Report for one of our projects – Download as a PDF document here.
Alt

Step 1

Clear the topsoil, take levels and lay compacted hardcore 150mm deep. Radon sump and pipework are laid at this stage.
Alt

Step 2

Place corners in position and set level.
Alt

Step 3

Continue placement of ring beam profiles. Trim profiles as necessary to achieve a tight fit.
Alt

Step 4

Place three layers of floor insulation sheets over the remaing foundation. Overlap sheets to achieve continuity of insulation. Secure with pins provided.
Alt

Step 5

Install steel through the ring beam profiles and place steel mesh reinforcement according to our structural engineer's design (supplied)
Alt

Step 6

Insulated foundation system is now complete and ready to take 100mm concrete.